Preventing River Pollution from Farming Activities in the Dommel and Warmbeek River Basin
Summary
Creation of natural buffer zones of 6 to 12 metre grass strips, to be managed by local farmers, preventing harmful fertilisers and pesticides from poluting the river water, improving water quality and protecting the biodiversity of the river basin.
Background
Farming activities in the Dommel & Warmbeek river basin have resulted in run-off of some residues from fertilizers & pesticides into the river. To combat this problem, seven municipalities in the province of Limburg, in collaboration with the Dommelvallei Water Management Agency, agreed to join forces with local farmers, to find ways to protect & improve water quality & biodiversity. The creation of natural grass buffer strips along watercourses was identified as a viable solution to the problem
Objective
The main objectives were: to encourage local farmers to create brook banks along the watercourse, thereby preventing water pollution and protecting river water quality; to stimulate cooperation amongst farmers & the local authorities in managing and maintaining the brook banks in a sustainable way; and to promote the implementation of similar projects in other municipalities.
Main activities
Activities included: (i) Creation of buffer zones (6 to 12 metre wide-strip grass, free of manuring and pesticides) between fields or arable land and watercourses (ii) Encouraging farmers to sign a 'Brook Bank Management Agreement' with local Municipalities; (iii) Assistance to farmers, both to complete the administrative requirements and to manage and maintain the brook banks; (iv) Promotion of the scheme within the region and particularly to other Municipalities.
Results & Benefits
The buffer zones created by the project offer benefits for water quality and biodiversity, allowing for an easier management of the brook banks. The management agreements were concluded for a total of 11.5 km, nearly doubling the extension of the existing buffer zones. In addition the project stimulated cooperation between farmers and local authorities and encouraged other farmers to join the scheme, contributing at the same time to improving the image of agriculture and of the region.
Lessons learnt
The employment of a project manager, who acted as coordinator at local level, allowed many problems to be solved, particularly at the start of the project. The project manager also informed many farmers directly about the project, encouraged them to sign management agreements and helped them resolve conflicts and administrative problems that would otherwise have prevented them from participating in the project.
Project location and other information
Flanders, 7 municipalities in the province of Limburg
Region
Prov. Limburg (B)
RDP Territory
Flanders
Total project cost (€)
565.800
Contact name
Watering De Dommelvallei, Industrieweg 8 bus 2, 3990 Peer, Belgium
Languages for contact
English, Dutch
At a glance
Country
Belgium
Final beneficiary type
Individual farmers, Public/local authorities
Budget range
> €500 000
Start date:
01/03/2007
End Date:
01/03/2010
Theme / Measure:
Environment and Sustainable Resource Management
Sustainable use of agricultural land
214. Agri-environment payments
Keywords:
Agri-environment, Biodiversity, Environmental education, Water
Last update
23/02/2012